Collins Park Water Treatment Plant
Have Questions about Harmful Algal Blooms?
headerProjects
Waterworks
Projects
View
Projects
Title
Description
Current Status
Budget
Photos
Residual Solids and Lagoon Improvements
(Facilities replacement, upgrades and modernization)
Ensures the capability to transfer, dewater and store residual solids from water treatment plant processes for future reuse and disposal. Phase 1 of the work includes improvements to spent lime Lagoon A piping, embankments, inlet and outlet structures, and overflows as required by the Ohio Department of Natural Resources. Phase 2 work includes refurbishment of the plate and frame presses and sludge thickener tanks.
Status Phase 1: Completed

Status Phase 2: Under Construction

Estimated Completion: 2020

Project Cost, Phase 1: $1,953,000

Project Budget, Phase 2: $6,000,000

Heatherdowns Pumping Station Improvements
(Facilities replacement, upgrades and modernization)
Mechanical, electrical and structural improvements that will restore the reliability and efficiency of the pumping facility to maintain system pressures within the southwestern portions of the City. Work includes rehabilitation of pumps and check valves, electrical equipment replacements, HVAC upgrades and structural refurbishment.
Status Phase 1: Completed

Status Phase 2: Completed

Project Cost, Phase 1: $3,520,000

Project Cost, Phase 2: $2,896,000

West and East Plant Roof Replacement (Facilities Replacement, Upgrades and Modernization)
Provides a safe, secure environment for the protection of critical treatment processes and staff, as well as ensuring the long-term structural integrity of the existing buildings. Work includes removal and replacement of concrete roof panels and roofing materials; replacement of corroded steel support elements; and improvements to heating, ventilation and dehumidification and electrical systems.
Status:
Completed

Project Cost: $14,536,000

New Disinfection Facilities (Water Quality, Redundancy and New Buildings)
Replacement of existing facilities to significantly improve the capacity, reliability and safety of the chlorine disinfection systems. Work includes construction of new chlorine storage and feed building, feed equipment and solution piping, together with a new chlorine dioxide storage, generation, feed equipment and related feed piping.
Status:
Completed

Project Cost: $11,900,000